What's left, in order · revised Oct 4, 2026 · details in the Build Guide · source: Roadmap.md
Where we are: walls sheathed; rafters, ridge and bracing up; deck plywood and PSCL clips in hand. Before the deck: shim the gapped ridge joints, toe-screw the 10 interior rafters, collar ties (Collar Ties).
Roof (Build Guide Phase 4)
Then the roof is done. Temporary bracing can come out: ridge diagonals and props after the deck; wall braces whenever convenient after the deck; the spreader after the shingles (Ridge Bracing).
Walls and finish (Build Guide Phase 5)
Decisions still open
Needed for the roof (soon)
Eave fascia: flush with the shadow board, or raised ~7/8″ (before the eave trim)
Optional center-post rim supports (only worth it before shingling)
Needed before the wall felt
Window sill pan, sill board, stops, casing and drip cap
Door threshold detail
Gable vent model
Needed later
Wall-shingle nail length (1-1/4″ or 1-1/2″), before buying the coils
Cedar starter overhang (1″ vs 1/4″ in different docs), before the cedar shingles
Finish on the rafters and ceiling (needs re-visiting)