Roof Phase Order

Gibson St shed · full re-order list · updated October 1, 2026 · 3-tab asphalt shingles over a solid sanded-plywood deck

Canonical source: Roof_Phase_Order.md in the project root (§0 is the current plan). Edit that first, then update this page by hand.

Oct 1 status. All 14 rafters are cut (one was miscut; a replacement 2×6×12 is being bought Oct 2) and the test pair was fitted. The ridge is cut to 143-13/16″ with the RR-R brackets attached, and A35Z angles are installed at the 4 corner seats. Raising is planned for Oct 2. Exterior wall sheathing is finished on all walls. The Union black drip edge is decided and delivered. Plywood: the 7 sheets on Lowe's order #300901273261392512 were cancelled by Lowe's (the only line not delivered); re-ordered from Home Depot, delivered Oct 2. Detailed roof geometry and edge details: Roof Deck and Edge Details.
What changed Sep 30: the metal roof is out; GAF 3-tab shingles in Weathered Gray go on the same 19/32 sanded deck and ProArmor. The previous Lowe's delivery order is being cancelled and everything re-ordered from this list. The framing, connectors, deck and cedar trim are unchanged. It saves about $550–650. You give up lifespan and wind resistance; in return the cedar layering shows on all four edges and few or no nail tips come through the ceiling.

Order list

0 of 24 lines checked off

Tip: search a Lowe's Item # on lowes.com to go straight to the exact product ordered. Quantities assume a roof about 151″ wide (rake to rake) and about 70″ along each slope, confirmed after the test rafter pair. Lowe's stock changes quickly: if a line is unavailable, ask before substituting cedar (keep the fascia 1½″ Architectural Knotty) or the connectors.

1 · Lumber and deck

OrderedItemQtyNotes
2×6×12 #2 Prime KD Southern Yellow Pine
Lowe's Item #74168 · Model #37017
7Rafters: two per board, 14 total. Cut and test one pair first.
2×8×12 #2 Prime KD Southern Yellow Pine
Lowe's Item #76972 · Model #2P020812S4
1Ridge board, one continuous piece.
1×6×12 cedar board (⅞″ × 5½″)
Lowe's Item #7503 · Model #7500
3Five collar ties, 2 + 2 + 1. Use the clearest wood at the nailed ends.
2×8×12 Architectural Knotty cedar (1½″ × 7½″)
Lowe's Item #4321 · Model #39367
6Fascia: one per eave (seamless) + one per rake. Green: stack with spacers, cover the top only, until install.
2×4×12 cedar, green, rough (1¾″ × 3¾″)
Lowe's Item #4303 · Model #RCL220412
2Eave shadow boards.
2×4×8 cedar, green, rough (1¾″ × 3¾″)
Lowe's Item #4301 · Model #RCL220408
4Rake shadow boards. They now show below a thin drip edge, not a wide metal trim.
2×4×14 spruce-pine-fir
Lowe's Item #28512 · Model #24#2SE.14
2Temporary ridge-to-floor braces. The spare 2×4s on hand make the floor anchor blocks.
Plytanium 19/32 × 4×8 BCX sanded plywood
Lowe's Item #12221 · Model #NA
7Cancelled by Lowe's; replaced by a Home Depot order, delivered Oct 2. 6 + 1 spare. Roof deck, B face down as the ceiling. APA Table 36 lists it for combined roof deck and ceiling at 24″ spans. Not treated plywood. Check the stamp on delivery.

2 · Dry-in (needed day 2)

OrderedItemQtyNotes
Simpson PSCL 19/32 panel clips (Home Depot; Lowe's delivery was a week out)112 needed: one per rafter bay at the seam between the two courses of deck sheets.
Owens Corning ProArmor synthetic underlayment
Lowe's Item #577176 · Model #PROA
1 rollRoof underlayment, plus leftover strips for the fascia bands. Rated for up to 90 days of sun exposure with cap fasteners.
Stinger CH38-2 cap hammer tacker
Lowe's Item #133716 · Model #0136400
11″ cap + 3/8″ staple, so nothing pokes through the ceiling. Used again later for the wall felt.
Stinger 3/8″ StaplePac (Lowe's)
Lowe's Item #135715 · Model #0136420
1Already ordered separately (pickup). Needed on day 2.

3 · Connectors and fasteners (needed day 1)

OrderedItemQtyNotes
Simpson RR-R ridge rafter connector
Lowe's Item #5031364 · Model #RR-R
14 bought, 10 used (4 to return)Screw onto both ridge faces on the ground, after a trial assembly. Listed screws in the factory holes only.
Simpson H2.5AZ hurricane tie (ZMAX)
Lowe's Item #115180 · Model #H2.5AZ
10Interior rafter seats. The previous order had only 4. Trial-fit first.
Simpson A35Z framing angle, 4.469″ (ZMAX)
Lowe's Item #108717 · Model #A35Z
4 (8 needed)8 needed: 4 end seats + 4 ridge ends (the RR-R does not fit at the ends). 4 on hand; 4 more to be bought Oct 2. Not the shorter A34.
Simpson SD9112 connector screws, #9 × 1½″, 100-count
Lowe's Item #130014 · Model #SD9112R100
3 boxesEvery connector: RR-R 10 × 8 = 80, A35Z 8 × 12 = 96, H2.5AZ 10 × 10 = 100, so about 276 needed. 3 boxes on hand; 1 more box Oct 2.
Grip-Rite 2″ 13-gauge 304 stainless ring-shank nails, 1 lb
Lowe's Item #41976 · Model #MAXN62433
1Collar ties, hand-driven: 7 per end, 70 total. Pre-drill near the tie ends.
CAMO #8 × 3½″ 316 stainless trim screws, 100-count
Lowe's Item #7399147 · Model #0350190S
2Already ordered separately. Cedar fascia and shadow boards, ~150, impact-driven. Keep 1″+ from board ends.
—On hand: 3″ × .120″ HDG ring gun nails—Roof deck: 4″ on sheet ends and gable rafters, 6″ on the other rafters, into rafters only. ~325. Snap chalk lines on the rafter centers.

4 · Shingles and roof edge (needed after the dry-in)

OrderedItemQtyNotes
GAF Royal Sovereign 3-tab, Weathered Gray, algae-resistant
Lowe's Item #652996 · Model #0202880
7 bundles~5 for the field, plus the cut eave starter (~9 shingles), cut ridge caps (~11) and spares. No starter bundle needed.
Union Corrugating 2.38″ black aluminum drip edge, 10′
Lowe's Item #366868 · Model #BKA45TSRE
6All six edges, all one product. A thin black line against the Weathered Gray shingles; most of the shadow board shows. Confirm the listing says 10′ and a qty of 6 pieces (not packs). Made for asphalt-shingle roofs; nail with the 3/4″ roofing nails.
Loctite PL S30 roof & flashing sealant
Lowe's Item #68457 · Model #1618181
3Under each shingle end along the rakes (required), optional at the eaves, and over the last ridge-cap nail heads. Replaces roofing cement.
BHTOP 3/4″ × .120″ 15° wire coil roofing nails, 3,600 (Amazon)1 box~1,000 used. 6 per shingle. 3/4″ keeps the tips inside the deck. Scrap test first. Test-fire a coil in the nailer.
Freeman G2CN45 15° coil roofing nailer (Amazon)13/4″–1-3/4″. Also installs the cedar wall shingles later with stainless coil roofing nails, so no siding nailer.
Kobalt straight-cut snips
Lowe's Item #5300905 · Model #54384
1Cutting drip edge.

Cancel & return

Design

Roof assembly

3-tab shingles on ProArmor over the 19/32 sanded deck. Solid ridge with cut 3-tab caps; ventilation through two gable vents, chosen later.

Framing

Fourteen KD pine rafters at 6:12, the JCS end seat with no tails, a 2×8 ridge board on RR brackets, five cedar collar ties, H2.5AZ and A35Z seats.

Cedar trim

2×8 fascia with 2×4 shadow boards on all four edges. A thin black drip edge along the top; the cedar layering shows at the eaves and the rakes.

Ceiling

The sanded B face shows inside. The 3/4″ shingle nails stay inside the deck, and the 3/8″ cap staples don't reach the face.

Weight

About 1,160 lb of roof installed (Oct 1 takeoff; the earlier ~1,040 lb was low). The center-post dead load is about 360 lb (about 550 lb with snow). See Structural_Load_and_Connection_Assessment.md §11.

Trade-offs accepted

About 15–20 year life and weaker wind resistance than metal. The short smooth nails are below GAF's spec, so treat the warranty as void. No inspection is involved.

Roof edges and shingle details

Build sequence

Your father is helping for two days (likely mid-October, once everything has arrived). The limit is weather: the roof must be dry by the end of day 2. Status Oct 1: all 14 rafters are cut and the test pair was fitted; the ridge is cut with its RR-R brackets attached; the A35Z angles are on at the 4 corner seats. Raising is planned for Oct 2.

Current build sequence (asphalt)

  1. Temporary 2×4 ridge props (30-1/4″) on the inside faces of the gable plates.
  2. Ridge on the props.
  3. The 4 end rafters, with the ridge-end A35Z angles.
  4. Check the ridge is level and straight.
  5. Tack the 2×4×14 diagonal braces (ridge to floor).
  6. Fill the rafter pairs (RR-R at the ridge; H2.5AZ at the plate as each is set).
  7. Fasten the braces.
  8. Collar ties (5 × cedar 1×6, 7 ring nails per end).
  9. Deck: 19/32 sanded BCX, PSCL clips at the course seam, 3″ ring nails at 4″ (ends and gable rafters) and 6″ (intermediate rafters).
  10. ProArmor with the cap stapler: rakes wrapped; leave the bottom 6–8″ at the eaves loose. That's a temporary dry-in: rated for up to 90 days of sun exposure. A tarp is only a backup.
  11. Eave drip edge under the loose underlayment strip; rake drip edge over the underlayment.
  12. Gable enclosure (plywood strips and band).
  13. Fascia and shadow boards.
  14. Shingles: scrap test, starter, 6 nails per shingle, PL S30 at the rakes, ridge caps.
  15. Gable vents later; the temporary bracing comes out last.

Storage until the build

Still open

Fastener and connector reference

PartUsed forInfo sheets
Simpson RR-R ridge rafter connectorRafter to ridge, 10 used (14 bought; 4 to return). Slopes up to 30°; minimum 2×6 rafter; interlocking top flanges for back-to-back pairsSimpson product page (UK site; the US page didn't turn up) · Simpson datasheet (PDF) · US spec summary. Fasteners: 4 into the ridge + 4 into the rafter, 0.148 × 1½″ nails or SD9112
Simpson H2.5AZ hurricane tie (ZMAX)Interior rafter seats, 10Product page · Installation guide. Rafter flange toward the ridge; plate flange's arrow line aligned per the guide
Simpson A35Z framing angle (ZMAX)End rafter seats 4 + ridge ends 4 (8 total)Product page · Installation guide. 12 SD9112 per angle; has a bend slot for field bends
Simpson SD9112 Strong-Drive SD connector screwEvery connector aboveProduct page · Approved-connector table. #9 × 1½″, ¼″ hex drive. Use only these in connector holes
Simpson connector general notesInstallation rules for all connectorsGeneral notes
Simpson PSCL 19/32 panel clipDeck course seam, 12Product page
Grip-Rite PrimeGuard Max 2″ 13-ga 304 stainless ring nailCollar ties, 7 per endLowe's listing
3″ × .120″ HDG ring gun nails (on hand)Roof deck, 4″/6″APA guide, Table 32 (deck nailing) and Table 36 (sanded deck as ceiling)

Sources